Pella Lutheran Church. Link to Home.
Link to News. Link to Calendar. Link to Staff. Link to Ministries. Link to Sermons. Link to Lambert.

 

AMBASSADOR NEWSLETTERS

 

2005 Newsletters

 

2006 Newsletters

 

2007 Newsletters

 

2008 Newsletters

 

2009 Newsletters

 

January 2010

 

February 2010

 

March 2010

 

April 2010

 

May 2010

 

June 2010

 

July 2010

 

August 2010

 

September 2010

 

October 2010

 

November 2010

 

December 2010

News.

BUILDING NEWS!!

June 2010

Our new building will have Geothermal heating and cooling.  A total of 48 wells are being drilled (each 200 feet deep) to where the temperature is about 55 degrees year round.  This will provide enough heating and cooling capacity not only for our new building but also for our existing sanctuary and basement as well!

 

The "footings" for the foundation of our Fellowship Hall are being constructed...

 

We also have pictures of our GROUNDBREAKING on April 18, 2010 and of the DEMOLITION of our old Office and Sunday School building in May!

CONSTRUCTION MEETING 8/25/10

Attendance: Pastor George, Pastor Charlane, Becky Reidle, Bill Evanson, Nancy Dynneson 

  • The contracted plumber has begun work on our project. With this progressing, soon they will be able to pour floors. Bill is going to contact Gary Johnson again as he has not yet received the drawings with the layout joints for the floors.

  • The beams are here. They are unfinished, but Kringen's will finish them once they are installed. The roof material is also here. They are awaiting the arrival of the roof trusses.

  • They are hoping to make the last pour to the foundation wall tomorrow, which will connect all the footings.

  • The brick layer will be in to lay the 1st floor for the elevator shaft.

  • We discussed the bill from Qwest for the moving of the pedestal. There was no charge for the line cut, as no one lost service. There is a bill for moving the pedestals. The work for doing this is complete. Pastor George will check with Jessica Johnson at Thrivent, as we may use the money for soft costs to pay this, rather than treating it as a change order which would use contingency funds. Requesting a change order then makes it more costly as Kringen's has to treat Qwest as a sub-contractor and add in insurance cost. The difference would be about $200 plus a cost for Qwest of $2600. Pastor George will follow up to see what is the best way to handle this.

  • Gary Johnson will be back for a site visit Wednesday Sept. 8 and Thursday Sept. 9. Pastor George will schedule a meeting the the Kitchen Committee on Wednesday, and the Interior Committee on Thursday. Bill is wanting a final decision on the window finishes, so he can get these ordered soon.

  • The next construction meeting will be at 8 AM on Thursday Sept. 9.

Submitted by:

 Nancy Dynneson

Click HERE for previous Construction Meeting Minutes

 

Click HERE to see a list of the details of this Building Project as adopted by the Building Committee on April 15, 2010.

 

Click HERE to see our proposed new building plans!!

 

Pastor Josh and Susan Magyar

Click HERE to read an update from Pastor Josh and Susan Magyar on their ministry to Morogoro, Tanzania!