Attendance:
Randy Jones, Pastor George, Pastor
Charlane, Bill Evanson, Nancy
Dynneson
The electrical
switch has been installed. There was
some “shake up” damage to this unit.
This will be replaced by the
supplier, but the original was
installed to move the project
forward and provide for a permanent
power source which is required for
the elevator to be installed.
Pastor George
stated that the new area had been
used for a wedding reception
Saturday the 10th and
this went well. There were toilets
in the bathroom, but the sinks were
not hooked up yet. The area was used
for Sunday AM coffee and those in
attendance were excited to see what
is complete.
Pastor George
also stated the Teresa Anderson has
been in contact with the architect
regarding the tile in the nursery.
It is not the correct color, and the
subcontractor will remove it and
install the correct tile.
Nancy had some
questions for Bill that she has been
asked frequently and here are the
responses:
·
There are two sumps in the elevator
shaft, so should one malfunction,
there is a backup.
·
The water entering the shaft seeps
in slowly and will eventually
activate the sump. Thus, when
the sump
activates, there is a larger
quantity of water to pump. This
accounts for the “river” of
water noted
running down Lincoln.
·
There is about a 4 foot dead space
below the elevator itself. Because
of this, should Sidney continue to
experience a high water table, if
there was a power outage, it would
be quite a time before the shaft
actually filled to the level of the
elevator.
·
The end of the canopy will be
covered by the siding used in the
other areas. It will be installed
once they receive a round vent that
is pre-finished to match the siding.
This goes in the center of the end
of the canopy and a cross will be
constructed within it.
Bill presented
some tentative dates for the
project:
1.
Countertops are scheduled to arrive
September 15th.
2.
The hollow metal frames for the
doors are scheduled for arrive
September 20th.
3.
They are hoping to have the Glue-lam
beams stained before the 29th
of September.
4.
The wood trim and ceilings are
scheduled to arrive September 29th.
5.
The elevator is scheduled for
installation October 17th.
Bill has contacted the elevator
supplier and should an opportunity
arise that they could install
sooner, they will work toward that.
Bill stated that the current lift
would be left in place until the new
elevator is installed and inspected.
When they can remove the lift,
Kringen Construction will work on
all the changes to the narthex at
that time.
6.
The wood doors are scheduled to
arrive October 20th. Bill
is hoping that most other work will
be done when the doors arrive, so
the install will basically be the
only job left, along with the
narthex.
7.
The bi-fold panel doors are
scheduled to arrive October 24th,
and because of their size, that
install will take a little more
time.
Pastor George
and Bill discussed when Mr. Fasig
should plan on returning to paint.
They established a time and Pastor
George will communicate that to Mr.
Fasig.
We discussed a
final completion date, and Bill
stated he is hoping this will be
November 1. We discussed the need to
get things wrapped up in a timely
manner to allow for the final
financing. This should not be an
issue.
Pastor George
stated that Gary Johnson will be on
site again once the wood arrives for
install. He will contact this group
when a date is set.
Pastor George
questioned if Bill felt it would be
possible to plan for the meal for
second capital campaign wrap-up in
the new area. Bill said this should
not be a problem. The meals planned
for 10/9 and 10/13 will be in the
new construction. This is an
opportunity for everyone to see the
results of the first campaign, while
moving forward to the second.
Respectfully
submitted by:
Nancy Dynneson